Notice

City Of Columbus Jerry Hammond Center 1111 E. Broad St. Boiler Replacement

websitecols. 1111 e. broad1

Location: Columbus, Ohio
Client:

City of Columbus

Description:

This project involves asbestos abatement and the replacement of

three boilers constructed in 1963, each with a 2,800,000 BTUH

(British thermal units per hour) capacity. HVAC design included

demolition work, temperature controls, heating water piping,

boilers, primary and secondary pumping, pressure-type flue,

expansion tank, and HVAC balancing. Electrical design included

work to support the HVAC work, including control wiring, starters,

and disconnect switches.


The replacement is being performed during the winter, and involves

several phases of construction to allow the building to operate without

any interruption due to loss of heat. The new boilers are being installed

while two of the three existing boilers continue to operate. Once the

new boilers are operational, the existing boilers will be removed.

Firm's Responsibility:

Mechanical and Electrical Engineering Services