Kilbourne Middle School
about this project
Still under construction.
McCord Middle School
about this project
Still under construction
Worthingway Middle School
about this project
Fusce at massa nec sapien auctor gravida in in tellus. Integer tempus, elit in laoreet posuere, lectus neque blandit dui, et placerat urna diam mattis orci.
Perry/Phoenix Middle School
about this project
This project involves MEP/FS engineering design for the additions and renovations of four existing middle schools for the Worthington City School District. MEP/FS systems were designed in accordance with the latest version of the Ohio Building Codes.
RDFA’s role was to provide the Mechanical, Electrical, Plumbing and Fire Protection design for this project, including site lighting, and Construction Administration in support of the Architect.
Notable engineering features of this Project:
Perry/Phoenix MS: 125,525 SF, Worthingway MS: 101,423 SF
McCord MS: 37,110 SF, Kilbourne MS: 13,051 SF
Construction Budget: $56,293,190